Nashik Tourism Subsidy for Expanding Hotels, Resorts and Homestays Before Kumbh 2027

5 days ago
8 min read

If you run a hotel, resort, lodge, homestay or agro-tourism unit in Nashik district and want to add rooms before the Kumbh, the Nashik tourism subsidy under Maharashtra's Tourism Policy 2024 can pay back a meaningful part of that capex. It will not fund the construction itself, and the rules for expanding an existing unit are stricter than most owners expect.


The Simhastha Kumbh Mela opened with the flag-hoisting on 31 October 2026. The State Government has announced the main Amrit Snan days as 2 August, 31 August and 11 September 2027 (12 September at Trimbakeshwar). That leaves about nine months to build and open new rooms.


Godavari river ghats in Panchavati, Nashik, with stone steps and temples along the bank
The Godavari ghats in Panchavati, Nashik, the focus of the Simhastha 2027 Amrit Snan days.

This guide follows the Tourism Policy of Maharashtra 2024, GR No. TDS-2022/09/CR No 542/Tourism-4 dated 18 July 2024, as amended and published by the Directorate of Tourism (DoT) in June 2025. It covers existing units on land that is already NA.


Which Nashik tourism subsidy zone is your taluka in?

Zone B names the Municipal Corporations of Nashik, Pune, Chhatrapati Sambhajinagar and Nagpur. Zone C is the rest of Maharashtra outside the Mumbai region. A further band, STZ/STD, applies only to specially declared tourism zones or districts.


Area

Zone

Note

Nashik Municipal Corporation limits (Nashik city, Nashik Road, Panchavati, Cidco, Satpur)

B

Named in the policy

Nashik taluka outside NMC limits, including Deolali Cantonment

C

Check which body you pay property tax to

Malegaon taluka, including Malegaon Municipal Corporation

C (verify)

A corporation, but not named in Zone B

Igatpuri, Trimbakeshwar, Sinnar, Niphad, Dindori, Peth, Surgana, Kalwan, Deola, Baglan, Nandgaon, Chandwad, Yeola

C

Includes municipal council towns

Special Tourism Zone or District

STZ/STD

None notified for Nashik that we could find


Two cautions. On a plain reading Malegaon is Zone C, because Zone B lists only four corporations by name; get DoT to confirm. And as of 3 November 2026 we found no notification declaring any part of the district a Special Tourism Zone, for the Kumbh or otherwise.


Shikhara of the Trimbakeshwar temple with its flag against a pale sky, Nashik district
Trimbakeshwar, like every taluka outside Nashik Municipal Corporation limits, falls in Zone C.

Unit types that qualify and their minimums

Annexure C of the policy defines each eligible unit:


Unit

Minimum under the policy

Hotel

10 lettable rooms with attached bathrooms; 1- to 5-star category certificate; Travel for LiFE certification

Resort

10 lettable rooms with attached bathrooms; 35% air-conditioned unless the location does not need it; 4 listed facilities such as a pool or conference room

Homestay or B&B

Guests stay in the owner's residence; DoT registration; B&B needs at least 1 room

Agro-tourism unit

1 acre, 2 lettable units, a farm experience, DoT registration

Tented accommodation

Fixed tents or pods with attached toilets, power, water and drainage

Restaurant

10 seats with washrooms, plus FSSAI and other licences


Every eligible unit must be registered with DoT or the Union Ministry of Tourism.


Not registered, or below the minimum today?

The expansion route is written for units that are registered with DoT and were operating on or before the 2024 policy. If you are not registered, register now, but get DoT's written view on whether a fresh registration meets that condition before committing capex. An 8-room lodge does not meet the 10-room definition, and the policy does not say whether expanding past 10 rooms cures that. Registered homestays have a separate route under Note 6 for revamping or adding rooms.


Hotel room with a double bed, side table and lamp
Under an expansion, incentives apply only to the rooms and facilities you add.

Expansion rules: 20% or 50%?

Here the policy contradicts itself. Notes 3 and 4 below Table 6 say an expansion must be at least 20% of existing capacity. Paragraph 29.5.3(4) and the Annexure C definition of 'Expansion of Tourism Project' both say more than 50% of existing capacity, such as rooms.


Two of the three references say 50%, and one is the definition DoT will test your file against. Plan for more than 50%: a 20-room resort should add at least 11 rooms, not 4. The other rules:


  • Incentives apply only to the expansion portion, with Eligible Capital Investment (ECI) worked out for the new component alone.

  • A Prior Eligibility Certificate (PEC) must be obtained during construction, and a Final Eligibility Certificate (FEC) after operations begin. Both are mandatory.

  • Apply for the eligibility certificate within 180 days of starting operations.

  • ECI covers buildings, MEP, furniture, equipment, waste treatment and renewable energy. Land, consultants' fees, capitalised interest and working capital are excluded.

  • Note 1 allows capex of the five years before COD; paragraph 29.5.2 says four. Work with four.

  • The extra 5% for women, SC and ST entrepreneurs is written for new units only.


Nashik tourism subsidy: Zone B vs Zone C incentives

Almost every expansion will sit below the mega-project threshold of ₹200 crore in Zone B and ₹125 crore in Zone C. For these units:


Incentive

Zone B (within NMC)

Zone C (rest of district)

Capital investment incentive

25% of ECI

30% of ECI

Ceiling for stay-based units

₹40 crore

₹40 crore

How it is paid

3 yearly instalments from COD

3 yearly instalments from COD

Eligibility period

7 years

10 years

SGST reimbursement

75% of net SGST

90% of net SGST

Electricity duty exemption

75%

100%

Stamp duty on sale, lease, mortgage

75% exemption

100% exemption

Stamp duty on mortgage loan

100% reimbursement

100% reimbursement


Yearly disbursement cannot exceed ECI divided by the eligibility period, and total incentives cannot exceed ECI. The two stamp duty rows overlap, so confirm with DoT whether you claim upfront through the stamp duty NOC or pay and claim back.


Rooms priced up to ₹7,500 a night now carry 5% GST without input tax credit, so SGST is 2.5% of tariff and the refund on a small expansion is modest. Our September 2025 post on Tourism Policy SGST incentives explains the refund. Adding a banquet hall? See our convention centre subsidy guide.


What already-NA land changes, and what it does not

  • NA permission: you already hold it. The Maharashtra Land Revenue Code (Second Amendment) Act, 2025 has removed the Collector's NA permission where the use is permitted under the Development or Regional Plan. Check that the permitted use covers hospitality.

  • NA tax: the same Act replaced annual NA assessment with a one-time premium, including for land converted earlier, collected before development permission. The policy exempts tourism projects from NA tax but is silent on this new premium. Ask before you pay.

  • Development charges: exempted for the tourism component. On an expansion this is a direct saving, because the revised building permission would otherwise attract charges on the new built-up area.

  • Additional FSI: outside Mumbai, up to 3 on a 12 m road, 3.5 on 18 m and 4 on 27 m, or the local DCR figure if higher, but not in Agriculture Zone or No Development Zone. Nashik is not among the premium-free areas, so expect a premium at 50% of the prevailing rate, payable in instalments.


Before finalising drawings, confirm with NMC, NMRDA or your municipal council that their regulations give effect to these provisions.


Building under renovation with scaffolding across its facade
Plan construction around a running property, and around the monsoon.

Month-by-month timeline to open before the Kumbh

Build in the monsoon, which slows site work from June, particularly in Igatpuri and Trimbakeshwar.


When

What to complete

Nov 2026

Confirm zone and DoT registration; run the 50% test; check road width and FSI; appoint architect; meet the bank

Dec 2026

Apply for PEC; file revised plans; request development charges exemption; term loan sanction

Jan 2027

Stamp duty NOC; mortgage; commencement certificate; start work with a separate capex ledger and meter

Feb–Apr 2027

Structure and services; file GST invoices and payment proofs monthly

May 2027

Finishes, furniture, fire NOC; apply for occupancy certificate

Jun 2027

Police, FSSAI and Shops licences; star classification; Travel for LiFE

Jul 2027

Open the new rooms. This is your COD

Aug–Sep 2027

Kumbh operations; keep records for the new block

By Jan 2028

Apply for FEC, within 180 days of COD

2028–2030

Capital incentive in three yearly instalments


Each instalment is paid at the end of a year from COD. With a July 2027 COD, the first falls due around July 2028 at the earliest, a year after the Kumbh peak. Fund the whole build through your own money and a term loan, and treat the subsidy as a repayment source.


Share the PEC with your banker so the instalments can be built into the repayment schedule. Stamp duty on the mortgage, 0.3% of a loan above ₹5 lakh and capped at ₹20 lakh, is reimbursed in full.


Worked illustration: a Zone C resort adding 12 rooms

An existing, DoT-registered 20-room resort outside NMC limits adds 12 rooms, 60% of capacity, clearing the 50% test. Figures are illustrative.


Item

Amount

Civil work for the new room block

₹2.40 crore

Electrical, plumbing and HVAC

₹0.60 crore

Furniture, fixtures and fittings

₹0.50 crore

Solar rooftop and STP upgrade

₹0.20 crore

Eligible Capital Investment (ECI)

₹3.70 crore

Architect, consultants, interest during construction (not eligible)

₹0.30 crore

Total project cost

₹4.00 crore

Term loan at 70%

₹2.80 crore

Capital incentive at 30% of ECI

₹1.11 crore

Paid in years 1, 2 and 3 after COD

₹37 lakh each

Mortgage stamp duty at 0.3% (reimbursed)

₹84,000

Yearly SGST refund (60% occupancy, ₹4,000 tariff)

About ₹2.4 lakh


Watch the annual ceiling. ECI of ₹3.70 crore over the 10-year Zone C period gives ₹37 lakh a year, which the capital instalment alone uses up in years 1 to 3. If DoT applies the ceiling to all incentives together, the SGST refund for those years could be held back, so model both cases. We have kept GST out of ECI because the policy's wording is unclear. In Zone B, the same project would earn 25%, or ₹92.5 lakh.


Common mistakes

  • Starting construction before applying for the PEC.

  • Planning a 20–49% expansion on the strength of the 20% note.

  • Mixing bills, meters and GST data of old and new blocks.

  • Counting land, consultants' fees or interest as ECI.

  • Assuming NA land means no premium or charges at sanction.

  • Missing the 180-day window after COD.

  • Expecting subsidy money before the Kumbh.


Documents checklist

Stacks of paper files and documents on a desk
Keep the expansion file separate from day one; DoT will ask for it.

  • DoT registration and proof of operations before July 2024

  • 7/12 extract or property card, NA order or development permission, and a lease of at least 15 years if leased

  • Existing and revised approved plans, commencement and occupancy certificates

  • Project report with the capacity working

  • Quotations, GST invoices and payment proofs for the expansion only

  • Architect's certificate of work done and the ECI working

  • Loan sanction letter, mortgage documents and stamp duty NOC

  • Fire NOC, police, FSSAI and Shops licences

  • Star or category certificate and Travel for LiFE registration

  • GST returns and the new block's electricity bills


Frequently asked questions

Can I claim incentives on my existing rooms?

No. Every benefit is limited to the expansion portion.


My resort is in Nashik city. Which zone applies?

Zone B if it is within Nashik Municipal Corporation limits: 25% capital incentive and 75% SGST reimbursement for seven years. Just outside, Zone C.


Is any part of Nashik a Special Tourism Zone for the Kumbh?

We found no such notification as of 3 November 2026. Check with DoT's Nashik regional office.


Will the subsidy arrive before the Kumbh?

No. The first instalment is due a year after COD, so a July 2027 opening means mid-2028 at the earliest.


Can I run a temporary tent camp instead?

September 2026 reports say the Nashik-Trimbakeshwar Kumbh Mela Authority has framed an SOP for private tent cities on sites of at least two acres, operating between March and December 2027. A temporary camp is not a permanent tented-accommodation unit under the policy, so do not assume incentives, and read the SOP itself.


Do homestays need a 50% expansion?

Note 6 gives registered homestays a route for revamping or adding rooms without stating a threshold. Confirm with DoT.


How DP Jadhav & Co. helps

Tourism Policy advisory is part of our government incentive practice. For an expansion we check zone and eligibility, prepare the project report and capacity working, file the PEC and FEC, set up a separate capex and GST trail for the new block, and work with your banker on the loan and stamp duty NOC. After COD, we track instalments and SGST refund claims.


Planning to add rooms before the Kumbh? Email contact@dpjadhav.com or call 9860804684 for a zone and eligibility check.



CMA Dhananjay Jadhav is the founder of DP Jadhav & Co., Cost & Management Accountants, Nashik, and Past Chairman of the ICMAI Nashik Chapter (2025–26).



Disclaimer: This is a general guide based on the Tourism Policy of Maharashtra 2024 (GR No. TDS-2022/09/CR No 542/Tourism-4, 18 July 2024) as amended in June 2025, and on announcements available on 3 November 2026. It is not legal or tax advice. Read the official policy document and confirm eligibility with the Directorate of Tourism before you invest.